Background
Area 2, a 3.26 ha site at Allerton Bywater Millennium Community, near Leeds.
Barratt Developments were selected as the preferred developer for this site.
Key information:
No of Units - 151
Homes per Ha 47.19
Number of Registered Social Landlord Affordable Homes - 30
First Time Buyer Initiative Units - 0
Key Dates:
- Last House Completion September 2009 (Projected)
- First Occupation May 2008 (Projected)
- First House Completion April 2008 (Projected)
- Start on Dwellings December 2006
- Start of Infrastructure April 2006
- Planning Approval Granted March 2006
- Planning Application Submission December 2005
Further information about the wider context of this proposed development is available on the Allerton Bywater Millennium Community page on the English Partnerships website.
View Barratt Developments Stage 2 bid
View Barratt Developments Stage 3 proposal
Website: Barratt Homes